Damage to Elem Archaeological Sites that Occurred Before an Archaeologist
was called in.
Jump to damage done by EPA after project archaeologist called in
Before
Parker & Assoc. Archaeological Research arrived at the project, the EPA had
already completed the Phase 1A portion of the project.
This involved demolition of existing homes and the removal of mine
tailings that had been used as fill under those homes.
Mechanical
excavation proceeded 30-60cm into underlying cultural soils after the mine waste
had been removed. In some instances these excavations went as deep as 8 to
10 feet into intact cultural soils.
In
areas where mine waste did not exist, damage to historic resources
included the use of a bulldozer to clear surface vegetation for the placement of
silt fences and driving track driven and tire driven trucks and equipment over
unprotected cultural soils.
On August 8th
2006, Archaeological Research took photographs and measurements of the open
excavations and graded areas that were still visible from the Phase 1A process.
These measurements revealed that approximately 7,000 cubic meters of cultural
soil had been destroyed.
The map below shows
the Elem Reservation along with black outlined areas of EPA archaeological
damage. Numbers on the map
correspond with the accompanying photos showing cut banks and excavations where
cultural soils had been removed. For scale, a meter stick with 10cm graduations is displayed
in most photos.
 

 
 
Resource Damage that Occurred During Archaeological Monitoring
When Archaeological Research
arrived on site, an excavation protocol was developed and agreed upon by all
parties (EPA, BIA, CH2MHILL, and the Tribe).
Click here to view Protocol
The protocol was developed to insure that the project met the requirements of
the National Historic Preservation Act and Archaeological Resource Protection
Act.
There were several occasions when CH2M HILL
contractors (acting under the direction of the EPA) did not follow the excavation protocol while working within the
boundaries of recorded archaeological sites.
As the project archaeologist was not permitted to stop project activities long enough to
conduct the necessary data recovery work, these instances caused unmitigated
damage to significant historic and prehistoric resources in violation of the
National Historic Preservation Act.
This section lists the
specifics of those cases and the amount of damage done. This map shows
areas of unmitigated damage
tied to the descriptions listed below.
1) Water Truck Haul Road Damage
On
8-19-06, The project archaeologist conducted a cultural resource inspection of the
project area and told CH2M HILL that the water trucks turning around near the
lake were causing damage to cultural site soils.
A request was made that the area be covered with geotextile material and base
rock to protect the underlying cultural soils from water and tire damage (violation of
protocol item #2). Almost
4 weeks of water truck traffic passed before the construction contractors
complied with this mitigation request. By
that time, a hole had been created in cultural soils that was 5 meters in diameter and
30cm deep.
This
unmitigated activity destroyed ~6m3 of cultural soil.
2) West Road Waste Removal Excavation
On 8-23-06, Tribal monitor
Sandy Thomas was stung by a bee while monitoring excavation in the cul-de-sac
area (by Lot 19) and had to leave her post for medical treatment.
Excavation did not stop as required by protocol and by the time the
project archaeologist could get to the area, excavation had proceeded through the mine waste and 60cm into cultural
soil (violation of protocol item #1).
Unknown volume of cultural
soil damaged.
On 8-24-06, excavation of mine
waste began before the Tribal monitor had returned from lunch break (by Lot 22). The project archaeologist (still eating lunch nearby) stepped in to monitor
the work so a work stoppage would not be necessary. A CH2M HILL employee told the project archaeologist that he couldn’t be in
the area. The archaeologist explained to the
employee that if he left, excavation would have to stop per the protocol.
The CH2M HILL employee refused to stop work when the archaeologist left
the area to report the incident to the CH2M HILL on-site director.
(violation of protocol item #1).
Unknown volume of cultural
soil damaged.
3) North Road Waste Removal Excavation
On 8-29-06, the project
archaeologist was
monitoring mine waste removal in front of Lots 2, 3, and 4.
He directed the contractors to stop digging when cultural soils were
encountered below the mine waste. His
directions were not followed and excavation removed both mine waste and all
underlying cultural soils (violation of protocol item #7).
Unknown volume of cultural
soil damaged.
4) Historic Feature Area Grading (west road)
On 8-30-06, mine waste removal
in front of Lot 23 excavated below the mine waste layer and at least 30cm into
cultural soil below the original 1906 ground surface.
CH2M HILL employees admitted that they were not taking toxic chemical measurements
but using visual cues only to determine the depth of the contaminated soil.
Their later measurements indicated that this pre-1906 cultural soil had
no contamination (violation of protocol item #7).
Unknown volume of cultural
soil damaged.
On 9-1-06, the project
archaeologist had a
field inspection and meeting with Mr. Emami (BIA Highway Construction Engineer)
to discuss the treatment of the sensitive historical features along the western
road. Mr. Emami expressed his concern that adequate compaction be
obtained prior to road construction. The
archaeologist explained that
if it became necessary to disturb the exposed historic features, then a data recovery
program would need to take place before the damage was done.
After more than an hour of discussion, an agreement was made to place a
thin layer of fine-grained fill over the historic features, then a layer of
geotextile material that would bridge the voids, allowing the proper compaction
of road fill. It was agreed that
this treatment would satisfy Mr. Emami’s concerns for road compaction and also
protect the underlying historical features.

On 9-9-06, under the direction of the EPA and CH2M HILL, a road grader ripped and
scraped through the historic features, destroying an area 16 meters wide by 80
meters long to a depth of 50cm. Six
of the seven pre-1906 historic features were destroyed along with an unknown
amount of prehistoric cultural soil. A
buried mortar was broken and then unearthed by the activity (violation of
protocol items #5 and #7).
At least 640m3 of
cultural soil was destroyed. To learn more about these historic features
click here: Historic Features
5) North Road Area Grading
On
9-9-06, Archaeologists John Holson and Kevin Bartoy of Pacific Legacy excavated through and
destroyed cultural soils in an area that was not scheduled for grading
(violation of protocol items #5 and #7).
Approximately 0.6m3 of cultural soil was needlessly destroyed.
On 9-11-06, CH2M HILL’s grader operator asked the project archaeologist if he could
grade through archaeological site soils along the northern road to level the
surface for the fill trucks.
Due to the cultural soils present, the archaeologist indicated that grading through this area
could not be done (see Protocol #2 and #3).
Within 20 minutes, the road grader was cutting through the area, damaging
cultural soils and unearthing a pestle (violation of protocol items #1, #2, and
#3).
Unknown volume of cultural
soil damaged.
6) Grading on Lots 1A and 1B
On 9-16-06, the project
archaeologist gave
instructions to a CH2M HILL subcontractor not to disturb cultural soils north of
the telephone pole and oak tree at the north end of Elem Drive in the areas of
Lots 1A and 1B. These instructions
were ignored and the subcontractor used a dozer to cut into the bank ~50cm deep
on both sides of the road (violation of protocol items #2 and #7).
Unknown volume of cultural
soil damaged.
7) Grading Between Lots 2 and 30
On 9-19-06, the big excavator returned to an area
where mine waste had already been removed and proceeded to excavate into
cultural soil to a depth of 60cm across an area 24 meters long by 14.4 meters
wide. No data recovery work was
allowed prior to this disturbance (violation of protocol items #2, #5, and #7).
Approximately
207m3 of cultural soil was needlessly destroyed.

In an effort to salvage a small amount of information from the damaged area, the
project archaeologist told CH2M HILL contractors to place the cultural soils on top of
clean fill that had already been deposited on Lot 1B.
The plan was to have the archaeological crew dry-screen through the soils
to recover any artifacts before the soils were taken to the Sulphur Bank Mine
waste deposit area. On 9-22-06,
Richard Sugarek (EPA Project Director) spotted the pile of cultural soil and had
it hauled to the mine waste disposal area before any screening could take place.
8) Lot 28 Water Truck Road Grading
On 9-22-06, grading to remove a layer of mine waste
from the water truck road on Lot 28 was conducted.
In anticipation of this work, a data recovery unit was excavated through
the mine waste and into the cultural deposit to a depth of 40cm (click Unit JK-1
to learn more about this unit). The size and
depth of the data recovery unit was based on core samples of soil
from various locations along the road. These
samples indicated a fairly shallow depth for the mine waste.
It was therefore determined that removing the waste would require
relatively shallow grading. The 1 x
2 meter archaeological unit was excavated to a depth of 40cm and recovered ~0.8m3
of cultural soil.
Sidewall profiles of the unit indicated mine waste to a depth of 5 to 15cm.
Mechanical grading was then done to
remove the mine waste. However,
once the mine waste was removed, grading continued, removing an additional 20 to
30cm depth of cultural soil.
This took place over an area
48 meters long and 3 meters wide destroying ~43.2m3 of cultural soil. Although data recovery is a way of
mitigating damage to archaeological resources as part of the Section 106
process, it is usually required that a “statistically valid” sample be
recovered from the area of impact.
The 0.8m3
data recovery sample effectively mitigated damage to
13.8m3 of cultural site soil. However the EPA's extensive
grading into intact archaeological soils caused 43.2m3 of
damage. This
means that 29.4m3 of damage occurred to this part of the site without
any mitigation (violation of protocol items #5 and #7).
9) Storm Drain Trench Misalignment
On 9-26-06, excavation of the
storm drain trench damaged intact portions of LAK-76.
The impacts of the storm drain trench were mitigated through a data
recovery program designed to recover a statistically valid sample of the area to
be disturbed. This mitigation
included the excavation of 7 data recovery units within the trench alignments. Project surveyors provided
the alignments for the placement of the archaeological units.
When the actual storm drain trenching was conducted, the trench was not on the
same alignment provided for the archaeological work, thereby destroying
a portion of the site that had not been mitigated (violation of protocol items
#5 and #7).
Unknown volume of cultural
soil damaged.
10) Lot 26 Soft Spot Grading (no photos obtained)
On 10-2-06, a Tribal monitor called to report that
excavation was taking place within undisturbed cultural soils in front of Lot
26. This work was apparently done
to remove a “soft spot” that had occurred due to over-watering by the water
trucks. Based on reports from John
Holson and Sandy Thomas, the hole was 5 meters by 6 meters and 1 meter deep
(violation of protocol items #5 and #7).
Ms. Thomas said that the soils
removed contained historic glass, metal and clamshell.
Approximately
30m3 of cultural soil was destroyed with no mitigation.
11) Lot 23 Water Line Trenching
On
10-4-06, excavation for a water line connection was conducted within cultural site
soil without the benefit of an archaeological monitor (violation of protocol
items #1, #5 and #7). Bones were
encountered.
Unknown volume of cultural
soil damaged.
Unmitigated Cultural Resource Damage Between August 22nd and
October 4th, 2006
Based on the above listed
violations of the excavation protocol, a minimum of 913m3 of cultural
soil was destroyed with no mitigation during the Phase 1B portion of the cleanup
project.
Earth Moving
Protocol for the
Elem Soil Remediation project
The Elem community is the
oldest community in Lake County. It
has existed in the same location for at least 6,000 years and may have roots at
this location that go back 12,000 years. This
means that important historic and prehistoric artifacts and sites cover much of
the property. Because there were no
written records, these sites contain the only information available about this
community’s past. These rules are
designed to allow this project to move forward without destroying Elem’s
cultural history. Not only are
these rules important to preserving their past, it is the law.
In order to comply with the National Historic Preservation Act (Section
106) and Title 36, Code of Federal Regulations, part 800.5 and 6 the items
listed below must be followed.
- No
grading, trenching, or excavating are to take place within the reservation
without Dr. Parker or his designee present.
- No
heavy equipment is to be parked, staged, or driven on natural soil.
All heavy equipment must stay on fill or asphalt.
If necessary, Dr. Parker will designate culturally “safe” areas
for equipment staging.
- While
bringing in and spreading new fill, heavy equipment is to ride atop the fill
rather than on natural ground. This
can be accomplished by pushing the fill ahead of the equipment.
- A
minimum of 8” of fill must be on the ground before compaction takes place.
Once an 8” layer of fill is down then the vibrating roller can be
used for compaction.
- There
is no natural obsidian on the reservation. If you see obsidian on the
ground, you are on an archaeological site. The artifacts belong to the Elem community.
Unless you are (or working for) a Registered Professional
Archaeologist, the Archaeological Resource Protection Act makes it illegal
to remove or deface a site or artifact.
- If
you see an artifact, point it out to Dr. Parker or the nearest Native
American monitor. If a monitor
can’t be found, place a pin flag at the location.
A system is in place to map and collect all sensitive artifacts for
curation in the tribe’s museum.
- If
an archaeological feature or site soil is encountered during excavation, and
in danger of disturbance, Dr. Parker may need to temporarily redirect
equipment to work in another area while the feature or site soil is mapped
and removed. Dr. Parker will
designate “resource safe” areas where fill removal can continue while
archaeological mapping and recovery take place at the primary work site.
Original passed and signed by the Elem Tribal Council
|